Project Progress Tracker
Umrao Cashmere
Laravel + Inertia JS + Filament build covering editorial storytelling, catalog experience, inquiry flow, and CMS operations.
Project Gantt
Delivery window at a glance
Key workstreams are mapped across the current delivery window so the client can see what has closed, what is active, and what is queued next.
Current target
25 March 2026
10-12 week scope window from finalized UI design
UI Development
100% complete
Backend Development
100% complete
Frontend Development
80% complete
Integration
55% complete
QA Testing
25% complete
Handover
0% complete
Project Summary
Scope A for Umrao Cashmere covers the brand site, commerce inquiry journey, backend management sections, CMS setup, launch content, and post-launch support. Work began on January 14, 2026 using Laravel, Inertia JS, and Filament. Homepage, About Us, Craftsmanship, and Cashmere UI moved early in the schedule, backend management sections were handled at the start by the backend team, and the remaining frontend pages were completed around mid-March. The open items now center on integrations, analytics, content setup, QA, and handover.
Roadmap View
Integration
Pending integrations and setup
The core site is built, but the final integrations and setup tasks still need implementation before the project can be treated as fully complete.
Final delivery phase
Reason: The remaining work is centered on service integration and launch-readiness items rather than large new page builds.
QA Testing
Regression and cross-flow validation
QA is the final control layer to confirm that UI, frontend, backend, and integrations behave correctly across the full project scope.
Runs after integration closure
Reason: The public journey, inquiry flows, admin modules, and integrations still need coordinated validation before release and handover.
Handover
Delivery and support handoff
The final handover should package the finished website, operational notes, and the agreed post-launch support period.
Final step after QA signoff
Reason: Handover depends on integrated services being completed and the QA pass being closed without blocking issues.
UI Development
Core UI pages completed
The visual direction started in January and continued through April as the brand-led pages and review-driven interface refinements evolved across the delivery cycle.
January to April 2026
Backend Development
Admin and CMS modules delivered
The backend team handled the administration and operations foundation in the initial part of the schedule so content and inquiry workflows could support the frontend.
Started at the beginning of the project
Frontend Development
Remaining pages delivered
The remaining public-facing scope was built through the later delivery window and reached working frontend completion around the middle of March.
Completed around mid-March 2026
Next Step
Close integration and pending service setup
WhatsApp and social integrations, analytics tooling, and final content setup should be closed before full QA signoff.
Estimated Completion
25 March 2026
10-12 week scope window from finalized UI design
Project Owner
Editorial Precision Studio
Delivery is split across UI, frontend, backend, integration, QA, and handover workstreams for easier review.
Step Details
Pending integrations and setup
Integration
In progress
WhatsApp and social media integration, Messenger setup, Google Analytics, Google Search Console, other analytical tools, and launch content work are the main remaining implementation items.
Why this phase is still open
The remaining work is centered on service integration and launch-readiness items rather than large new page builds.
What this means for you
The largest unfinished items are external integrations and launch setup rather than core page development.
Once these services are connected, the project can move cleanly into final QA and handover.
Attachments and proof of work
Need a clarification?
Use the dashboard update trail first, then escalate only if a delivery decision is blocked.